OPTIMIZATION OF CAFE AND SALON DEVELOPMENT PROJECT MANAGEMENT WITH PERT AND CPM METHODS AT PT DTD

Authors

  • Ryan Swastiputro Adinugroho Universitas Mercu Buana, Jakarta
  • Sugiyono Madelan Universitas Mercu Buana, Jakarta

DOI:

https://doi.org/10.31933/dijms.v3i1.919

Keywords:

Construction Project, PERT, CPM, cafe and salon.

Abstract

The construction of cafe and salon by PT DTD has been delayed in terms of time. The purpose of this study is to calculate the best time optimization and determine the critical path of the cafe and salon construction project at PT DTD. This research is an evaluation of a project that has been completed. The methods used are Critical Path Method (CPM) and Project Evaluation Review Technique (PERT).  The software used is POM-QM for Windows. The project runs for 15 months or 62 weeks from the initial target of the contractor being 8 months. Using POM-QM, from the PERT method, the optimum time for the project is 50 weeks. Project optimization can be carried out using PERT and CPM methods with POM QM software.

References

Aulia, M., & Priyo, M. (2015). Aplikasi Metode Time Cost Trade Off Pada Proyek Konstruksi: Studi Kasus Proyek Pembangunan Gedung Indonesia. Jurnal Ilmiah Semesta Teknika, 18, 30-34.
Barlow, J. F. (2005). Excel Models for Business and Operations Management. John Wiley & Sons, Ltd.
Cynthia, O. U. (2020). Implementation of Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM): A Comparative Study. International Journal of Industrial and Operations Research.
Dewi, S. (2017). Analisis Penjadwalan Proyek pada Pembangunan Gedung Sekolah SMK Pelayaran Hang Tuah Kediri dengan Metode Critical Path Method. Simki-Economic Vol. 01.
Dimyati, H., & Nurjaman, K. (2014). Manajemen Proyek. Bandung: CV Pustaka Setia.
Hamdan, D., & Kadar, N. (2014). Manajemen Proyek. Bandung: CV. Pustaka.
Heizer, J., & Render, B. (2009). Operation Management (Manajemen Operasi). Jakarta: Salemba Empat.
Herman, J., & Sugiyono. (2017). Penjadwalan Proyek untuk Mendapatkan Efesiensi Waktu dan Biaya di Unit Renovasia Apartmen The Bellezza Suites dengan Metode Critical Path Method (CPM) dan Program Evalution and Review Technique (PERT).
Heyzer, J., Render, B., & Munson, C. (2017). Operations Management, Sustainability and Supply Chain Management (12th ed.). England: Pearson Education Limited 2017.
Husen, A. (2009). Manajemen Proyek. Yogyakarta: Penerbit Andi.
Ishak, A. (2010). Manajemen Operasi. Yogyakarta: Graha Ilmu.
Latifah, S. (2020). Optimalisasi Manajemen Waktu dan Biaya Terhadap Pembangunan Proyek (Studi Kasus Penyelesaian Pembangunan Puskesmas 1 Batur CV. SENDO HOKAGE). Journal of Economic, Business and Engineering (JEBE).
Munibullah, M., & Sugiyono. (2017). Optimasi Time Cost Trade of Analysis (Studi Kasus: Qatar Charity Indonesia).
Nurhayati. (2010). Manajemen Proyek. Yogyakarta: Graha Ilmu.
Ramadhan, T., & Sugiyono. (2019). Analisis Optimalisasi Proyek dengan Menggunakan Metode PERT. Indikator: Jurnal Ilmiah Manajemen dan Bisnis.

Published

2021-10-15

How to Cite

Ryan Swastiputro Adinugroho, & Madelan, S. . (2021). OPTIMIZATION OF CAFE AND SALON DEVELOPMENT PROJECT MANAGEMENT WITH PERT AND CPM METHODS AT PT DTD. Dinasti International Journal of Management Science, 3(1), 188–201. https://doi.org/10.31933/dijms.v3i1.919